Massing Sample LibraryMassingCloud

Library / Healthcare

Vantage Point Ambulatory Surgery Center

A three-storey ambulatory surgery centre with four operating rooms, twelve pre-op/PACU bays and two floors of medical office above, built to FGI Guidelines and OSHPD-equivalent structural criteria.

Gross area95,900 sf
Storeys34.60 m floor to floor
Elements2,607193 data rows
Total dev cost$50.8M$530/sf
NOI$3.7M
Yield on cost7.26%+101 bps over a 6.25% cap

Download .mass · 2.8 MB Executive report All files

Issued drawings

Generated from the model — column positions, wall runs, space polygons and grid spacing are read out of the IFC — so a sheet cannot drift from the building it documents. ARCH-D, 5 of 22 registered sheets issued.

A1.01 — Overall Floor Plan Level 1
A1.01 Overall Floor Plan Level 1open full ↗
A2.01 — Building Elevations
A2.01 Building Elevationsopen full ↗
E2.01 — Power and Lighting Plan Typical Level
E2.01 Power and Lighting Plan Typical Levelopen full ↗
G0.01 — Cover Sheet and Project Data
G0.01 Cover Sheet and Project Dataopen full ↗
S2.01 — Framing Plan Typical Level
S2.01 Framing Plan Typical Levelopen full ↗

LOD record coverage

Share of IfcElement occurrences carrying each part of the record, read out of the IFC inside the container.

LOD stage100%
As-built record100%
Measured dimension100%
Manufacturer84%
Classification100%
Material84%

Manufacturer and material fall short of 100% by the same reason: an IfcOpeningElement is a void and an IfcElementAssembly is a grouping — neither is a thing anybody manufactures or pours.

Assemblies321
Reinforcing bars0
Fasteners1,083
Analytical members321
MEP ports321
Spaces3695,906 sf modelled

Programme

SpaceTypeLevelsArea % of gross
Operating rooms + sterile coreBack-of-House114,600 sf15.2%
Pre-op / PACUBack-of-House111,200 sf11.7%
Imaging and diagnosticsBack-of-House18,400 sf8.8%
Medical office suitesOffice246,700 sf48.7%
Building services and MEPMechanical315,000 sf15.6%

Cost and programme

Largest divisions

05 — Metals$4,550,90013.0%
03 — Concrete$3,919,10011.2%
23 — Heating, Ventilating & Air Conditioning (HVAC)$3,384,8009.7%
01 — General Requirements$3,279,8009.4%
09 — Finishes$3,150,7009.0%

Revised budget $35.0M · forecast at completion $35.2M · variance -0.74%.

Registers

Approvals9
Risks10
Phase gates8
Long-lead packages8
Sheets registered22
Sheets issued5

Unweighted risk exposure $5,972,600 and 200 days, against a carried contingency of 5%.

Schedule — 02 Mar 2026 to 22 Jun 2028, 28 months

PhaseTradeStartFinish Working days
Mobilization and site logisticsSiteworkMar 2026Apr 202624
Mass excavation and shoringSiteworkApr 2026Jun 202642
Foundations and below-gradeConcreteJun 2026Aug 202661
SuperstructureStructureAug 2026Feb 2027121
Building envelopeEnvelopeFeb 2027Jun 202791
MEP rough-inMEPJun 2027Oct 202797
Interior build-outInteriorsOct 2027Feb 202879
Finishes and fit-outFinishesFeb 2028Apr 202849
Commissioning and turnoverCommissioningApr 2028Jun 202842

Development pro forma

Uses of funds

Land acquisition$3,200,0006.3%
Hard cost$34,524,00068.0%
Hard cost contingency (5%)$1,726,2003.4%
Soft cost (24%)$8,700,04817.1%
Construction period interest$2,632,3745.2%
Total development cost $50,782,622100.0%

Returns

Stabilised value$59,003,818
Development profit$8,221,196
Unlevered IRR (7-yr)11.81%
Levered IRR (7-yr)15.30%
Equity multiple2.45×

Synthetic sample project. Figures are internally consistent and derived from one set of assumptions in tools/sectors.py — they are not market data.

Every file