Massing Sample LibraryMassingCloud

Library / Data Center

Northbridge Data Hall

A 12 MW colocation building: four 3 MW data halls on a raised floor, an electrical yard with N+1 generation, and a chilled-water plant sized for concurrent maintainability.

Gross area63,000 sf
Storeys18.50 m floor to floor
Elements1,014191 data rows
Total dev cost$127.5M$2,024/sf
NOI$10.3M
Yield on cost8.04%+129 bps over a 6.75% cap

Download .mass · 1.2 MB Executive report All files

Issued drawings

Generated from the model — column positions, wall runs, space polygons and grid spacing are read out of the IFC — so a sheet cannot drift from the building it documents. ARCH-D, 5 of 22 registered sheets issued.

A1.01 — Overall Floor Plan Level 1
A1.01 Overall Floor Plan Level 1open full ↗
A2.01 — Building Elevations
A2.01 Building Elevationsopen full ↗
E2.01 — Power and Lighting Plan Typical Level
E2.01 Power and Lighting Plan Typical Levelopen full ↗
G0.01 — Cover Sheet and Project Data
G0.01 Cover Sheet and Project Dataopen full ↗
S2.01 — Framing Plan Typical Level
S2.01 Framing Plan Typical Levelopen full ↗

LOD record coverage

Share of IfcElement occurrences carrying each part of the record, read out of the IFC inside the container.

LOD stage100%
As-built record100%
Measured dimension100%
Manufacturer84%
Classification100%
Material84%

Manufacturer and material fall short of 100% by the same reason: an IfcOpeningElement is a void and an IfcElementAssembly is a grouping — neither is a thing anybody manufactures or pours.

Assemblies121
Reinforcing bars0
Fasteners408
Analytical members121
MEP ports125
Spaces463,033 sf modelled

Programme

SpaceTypeLevelsArea % of gross
Data halls (white space)Back-of-House139,000 sf61.9%
Electrical rooms + UPSMechanical111,400 sf18.1%
Mechanical plantMechanical18,600 sf13.7%
Admin, security, MMROffice14,000 sf6.3%

Cost and programme

Largest divisions

26 — Electrical$21,682,80023.3%
23 — Heating, Ventilating & Air Conditioning (HVAC)$16,497,80017.7%
03 — Concrete$9,898,70010.6%
05 — Metals$8,799,7009.5%
11 — Equipment$6,851,2007.4%

Revised budget $93.1M · forecast at completion $94.1M · variance -1.13%.

Registers

Approvals9
Risks10
Phase gates8
Long-lead packages9
Sheets registered22
Sheets issued5

Unweighted risk exposure $13,793,900 and 295 days, against a carried contingency of 5%.

Schedule — 02 Mar 2026 to 24 Feb 2028, 24 months

PhaseTradeStartFinish Working days
Mobilization and site logisticsSiteworkMar 2026Mar 202621
Mass excavation and shoringSiteworkMar 2026May 202636
Foundations and below-gradeConcreteMay 2026Jul 202652
SuperstructureStructureJul 2026Dec 2026104
Building envelopeEnvelopeDec 2026Apr 202778
MEP rough-inMEPApr 2027Aug 202783
Interior build-outInteriorsAug 2027Nov 202768
Finishes and fit-outFinishesNov 2027Jan 202842
Commissioning and turnoverCommissioningJan 2028Feb 202836

Development pro forma

Uses of funds

Land acquisition$7,900,0006.2%
Hard cost$91,350,00071.6%
Hard cost contingency (5%)$4,567,5003.6%
Soft cost (19%)$18,224,32514.3%
Construction period interest$5,500,7304.3%
Total development cost $127,542,555100.0%

Returns

Stabilised value$152,000,000
Development profit$24,457,445
Unlevered IRR (7-yr)12.88%
Levered IRR (7-yr)16.45%
Equity multiple2.54×

Synthetic sample project. Figures are internally consistent and derived from one set of assumptions in tools/sectors.py — they are not market data.

Every file