Massing Sample LibraryMassingCloud

Library / Industrial

Ironline Distribution Center

A 340,000 sf cross-dock distribution building: tilt-up concrete panels, 40 ft clear height, 62 dock doors and a fitted office block at the northwest corner.

Gross area340,000 sf
Storeys112.20 m floor to floor
Elements3,286186 data rows
Total dev cost$46.5M$137/sf
NOI$3.1M
Yield on cost6.64%+89 bps over a 5.75% cap

Download .mass · 3.5 MB Executive report All files

Issued drawings

Generated from the model — column positions, wall runs, space polygons and grid spacing are read out of the IFC — so a sheet cannot drift from the building it documents. ARCH-D, 5 of 21 registered sheets issued.

A1.01 — Overall Floor Plan Level 1
A1.01 Overall Floor Plan Level 1open full ↗
A2.01 — Building Elevations
A2.01 Building Elevationsopen full ↗
E2.01 — Power and Lighting Plan Typical Level
E2.01 Power and Lighting Plan Typical Levelopen full ↗
G0.01 — Cover Sheet and Project Data
G0.01 Cover Sheet and Project Dataopen full ↗
S2.01 — Framing Plan Typical Level
S2.01 Framing Plan Typical Levelopen full ↗

LOD record coverage

Share of IfcElement occurrences carrying each part of the record, read out of the IFC inside the container.

LOD stage100%
As-built record100%
Measured dimension100%
Manufacturer85%
Classification100%
Material85%

Manufacturer and material fall short of 100% by the same reason: an IfcOpeningElement is a void and an IfcElementAssembly is a grouping — neither is a thing anybody manufactures or pours.

Assemblies405
Reinforcing bars0
Fasteners1,358
Analytical members405
MEP ports397
Spaces9339,986 sf modelled

Programme

SpaceTypeLevelsArea % of gross
Warehouse floorBack-of-House1316,000 sf92.9%
Dock and stagingBack-of-House114,000 sf4.1%
Office mezzanineOffice110,000 sf2.9%

Cost and programme

Largest divisions

03 — Concrete$7,263,20022.9%
05 — Metals$6,343,60020.0%
07 — Thermal & Moisture Protection$3,330,40010.5%
01 — General Requirements$2,346,0007.4%
26 — Electrical$1,936,9006.1%

Revised budget $31.7M · forecast at completion $32.0M · variance -0.80%.

Registers

Approvals8
Risks9
Phase gates8
Long-lead packages8
Sheets registered21
Sheets issued5

Unweighted risk exposure $4,128,900 and 165 days, against a carried contingency of 5%.

Schedule — 02 Mar 2026 to 24 Aug 2027, 18 months

PhaseTradeStartFinish Working days
Mobilization and site logisticsSiteworkMar 2026Mar 202616
Mass excavation and shoringSiteworkMar 2026Apr 202627
Foundations and below-gradeConcreteApr 2026Jun 202639
SuperstructureStructureJun 2026Oct 202678
Building envelopeEnvelopeOct 2026Dec 202658
MEP rough-inMEPDec 2026Mar 202762
Interior build-outInteriorsMar 2027Jun 202751
Finishes and fit-outFinishesJun 2027Jul 202731
Commissioning and turnoverCommissioningJul 2027Aug 202727

Development pro forma

Uses of funds

Land acquisition$6,800,00014.6%
Hard cost$31,280,00067.3%
Hard cost contingency (5%)$1,564,0003.4%
Soft cost (16%)$5,255,04011.3%
Construction period interest$1,589,0893.4%
Total development cost $46,488,129100.0%

Returns

Stabilised value$53,677,190
Development profit$7,189,060
Unlevered IRR (7-yr)11.13%
Levered IRR (7-yr)15.06%
Equity multiple2.47×

Synthetic sample project. Figures are internally consistent and derived from one set of assumptions in tools/sectors.py — they are not market data.

Every file