Massing Sample LibraryMassingCloud

Library / Residential

Harborview Residences

A 96-unit market-rate apartment building on a half-block infill site: five wood-framed residential levels over a concrete podium holding structured parking and 6,400 sf of ground-floor retail.

Gross area118,200 sf
Storeys63.05 m floor to floor
Elements5,480189 data rows
Total dev cost$37.1M$314/sf
NOI$2.4M
Yield on cost6.48%+123 bps over a 5.25% cap

Download .mass · 5.7 MB Executive report All files

Issued drawings

Generated from the model — column positions, wall runs, space polygons and grid spacing are read out of the IFC — so a sheet cannot drift from the building it documents. ARCH-D, 5 of 20 registered sheets issued.

A1.01 — Overall Floor Plan Level 1
A1.01 Overall Floor Plan Level 1open full ↗
A2.01 — Building Elevations
A2.01 Building Elevationsopen full ↗
E2.01 — Power and Lighting Plan Typical Level
E2.01 Power and Lighting Plan Typical Levelopen full ↗
G0.01 — Cover Sheet and Project Data
G0.01 Cover Sheet and Project Dataopen full ↗
S2.01 — Framing Plan Typical Level
S2.01 Framing Plan Typical Levelopen full ↗

LOD record coverage

Share of IfcElement occurrences carrying each part of the record, read out of the IFC inside the container.

LOD stage100%
As-built record100%
Measured dimension100%
Manufacturer92%
Classification100%
Material93%

Manufacturer and material fall short of 100% by the same reason: an IfcOpeningElement is a void and an IfcElementAssembly is a grouping — neither is a thing anybody manufactures or pours.

Assemblies240
Reinforcing bars3,600
Fasteners0
Analytical members636
MEP ports642
Spaces72117,994 sf modelled

Programme

SpaceTypeLevelsArea % of gross
RetailRetail16,400 sf5.4%
Parking / back of houseParking114,200 sf12.0%
Residential unitsResidential Unit579,600 sf67.3%
Amenity + circulationAmenity518,000 sf15.2%

Cost and programme

Largest divisions

03 — Concrete$4,065,00015.8%
09 — Finishes$2,705,80010.5%
06 — Wood, Plastics & Composites$2,668,40010.4%
01 — General Requirements$2,160,1008.4%
07 — Thermal & Moisture Protection$1,932,7007.5%

Revised budget $25.7M · forecast at completion $25.9M · variance -0.77%.

Registers

Approvals7
Risks9
Phase gates8
Long-lead packages7
Sheets registered20
Sheets issued5

Unweighted risk exposure $3,405,400 and 160 days, against a carried contingency of 5%.

Schedule — 02 Mar 2026 to 26 Apr 2028, 26 months

PhaseTradeStartFinish Working days
Mobilization and site logisticsSiteworkMar 2026Apr 202623
Mass excavation and shoringSiteworkApr 2026May 202639
Foundations and below-gradeConcreteMay 2026Aug 202656
SuperstructureStructureAug 2026Jan 2027113
Building envelopeEnvelopeJan 2027May 202785
MEP rough-inMEPMay 2027Sep 202790
Interior build-outInteriorsSep 2027Dec 202773
Finishes and fit-outFinishesDec 2027Mar 202845
Commissioning and turnoverCommissioningMar 2028Apr 202839

Development pro forma

Uses of funds

Land acquisition$2,800,0007.5%
Hard cost$25,413,00068.4%
Hard cost contingency (5%)$1,270,6503.4%
Soft cost (22%)$5,870,40315.8%
Construction period interest$1,789,2724.8%
Total development cost $37,143,325100.0%

Returns

Stabilised value$45,854,035
Development profit$8,710,711
Unlevered IRR (7-yr)11.82%
Levered IRR (7-yr)15.69%
Equity multiple2.59×

Synthetic sample project. Figures are internally consistent and derived from one set of assumptions in tools/sectors.py — they are not market data.

Every file