Massing Sample LibraryMassingCloud

Library / Mixed-Use

Foundry Row

A vertical mixed-use block: two levels of retail and structured parking podium carrying an eight-storey residential tower, with a shared amenity deck at the podium roof.

Gross area246,300 sf
Storeys103.40 m floor to floor
Elements9,604194 data rows
Total dev cost$87.0M$353/sf
NOI$5.7M
Yield on cost6.52%+102 bps over a 5.50% cap

Download .mass · 9.7 MB Executive report All files

Issued drawings

Generated from the model — column positions, wall runs, space polygons and grid spacing are read out of the IFC — so a sheet cannot drift from the building it documents. ARCH-D, 5 of 20 registered sheets issued.

A1.01 — Overall Floor Plan Level 1
A1.01 Overall Floor Plan Level 1open full ↗
A2.01 — Building Elevations
A2.01 Building Elevationsopen full ↗
E2.01 — Power and Lighting Plan Typical Level
E2.01 Power and Lighting Plan Typical Levelopen full ↗
G0.01 — Cover Sheet and Project Data
G0.01 Cover Sheet and Project Dataopen full ↗
S2.01 — Framing Plan Typical Level
S2.01 Framing Plan Typical Levelopen full ↗

LOD record coverage

Share of IfcElement occurrences carrying each part of the record, read out of the IFC inside the container.

LOD stage100%
As-built record100%
Measured dimension100%
Manufacturer92%
Classification100%
Material92%

Manufacturer and material fall short of 100% by the same reason: an IfcOpeningElement is a void and an IfcElementAssembly is a grouping — neither is a thing anybody manufactures or pours.

Assemblies400
Reinforcing bars6,400
Fasteners0
Analytical members1,070
MEP ports1,056
Spaces120246,257 sf modelled

Programme

SpaceTypeLevelsArea % of gross
RetailRetail242,000 sf17.1%
Structured parkingParking231,000 sf12.6%
Residential unitsResidential Unit8141,300 sf57.4%
Amenity deck + BOHAmenity832,000 sf13.0%

Cost and programme

Largest divisions

03 — Concrete$9,855,90016.8%
09 — Finishes$5,751,7009.8%
01 — General Requirements$5,093,5008.7%
06 — Wood, Plastics & Composites$4,630,4007.9%
05 — Metals$4,401,8007.5%

Revised budget $58.6M · forecast at completion $59.1M · variance -0.79%.

Registers

Approvals8
Risks9
Phase gates8
Long-lead packages7
Sheets registered20
Sheets issued5

Unweighted risk exposure $8,566,300 and 180 days, against a carried contingency of 5%.

Schedule — 02 Mar 2026 to 26 Oct 2028, 32 months

PhaseTradeStartFinish Working days
Mobilization and site logisticsSiteworkMar 2026Apr 202628
Mass excavation and shoringSiteworkApr 2026Jun 202649
Foundations and below-gradeConcreteJun 2026Sep 202669
SuperstructureStructureSep 2026Apr 2027139
Building envelopeEnvelopeApr 2027Aug 2027104
MEP rough-inMEPAug 2027Jan 2028111
Interior build-outInteriorsJan 2028Jun 202890
Finishes and fit-outFinishesJun 2028Aug 202856
Commissioning and turnoverCommissioningAug 2028Oct 202849

Development pro forma

Uses of funds

Land acquisition$7,200,0008.3%
Hard cost$57,880,50066.5%
Hard cost contingency (5%)$2,894,0253.3%
Soft cost (23%)$13,978,14116.1%
Construction period interest$5,048,2845.8%
Total development cost $87,000,950100.0%

Returns

Stabilised value$103,088,641
Development profit$16,087,691
Unlevered IRR (7-yr)11.33%
Levered IRR (7-yr)14.32%
Equity multiple2.38×

Synthetic sample project. Figures are internally consistent and derived from one set of assumptions in tools/sectors.py — they are not market data.

Every file