Application and Certificate for Payment

Following the AIA G702 line structure

Owner
Riverside Health Partners LLC
200 Capitol Mall, Suite 1400, Sacramento, CA 95814
Contractor
Northgate Builders
Architect
Ferris & Partners Architects
55 Front Street, Sacramento, CA 95814
Project
2026-014 — Riverside Medical Office Building
Address
1400 Riverside Drive, Sacramento, CA 95811
Contract
PC-2026-014
Contract date
2026-01-12
Application no.
5
Period to
2026-06-30
Application date
2026-06-30
Retainage
5.00% on work, 2.50% on stored material
1Original contract sum$4,850,000.00
2Net change by change orders$148,000.00
3Contract sum to date (1 + 2)$4,998,000.00
4Total completed and stored to date$2,915,000.00
5aRetainage, 5.00% of completed work$145,750.00
5bRetainage, 2.50% of stored material$0.00
5Total retainage (5a + 5b)$145,750.00
6Total earned less retainage (4 − 5)$2,769,250.00
7Less previous certificates for payment$2,469,475.00
8Current payment due (6 − 7)$299,775.00
9Balance to finish, including retainage (3 − 6)$2,228,750.00

Change order summary

Approved in previous months — additions$148,000.00
Approved in previous months — deductions$0.00
Approved this month — additions$0.00
Approved this month — deductions$0.00
Net change (to line 2)$148,000.00

Contractor's statement

The undersigned contractor states that the work covered by this application has been completed in accordance with the contract documents; that the amounts shown have been paid by the contractor for work for which previous certificates were issued and payments received; and that the payment shown as currently due is now properly owing.

 
Contractor — authorised signature
 
Printed name and title
 
Date

State of ______________________    County of ______________________

Subscribed and sworn to before me this ______ day of ______________, 20____.

 
Notary public
 
My commission expires

Architect's certificate

Based on observations at the site and on the data in this application, the architect certifies to the owner that to the best of the architect's knowledge the work has progressed as stated, that its quality is in accordance with the contract documents, and that the contractor is entitled to payment of the amount certified below.

Amount certified  

Where the amount certified differs from the amount applied for, initial the figures on this application and on the continuation sheet that have been changed to match, and attach an explanation.

Architect — authorised signature
Date

This certificate is not negotiable. It is payable only to the contractor named above. Issuing, receiving or accepting payment does not prejudice any rights of the owner or the contractor under the contract.

Continuation Sheet

2026-014 — Riverside Medical Office Building · Application no. 5 · 2026-06-01 to 2026-06-30

A
Item no.
B
Description of work
CSI C
Scheduled value
D
From previous application
E
This period
F
Materials presently stored
G
Total completed and stored
%
(G / C)
H
Balance to finish
I
Retainage
001 General conditions 01 $340,000.00 $168,000.00 $42,000.00 $210,000.00 61.76% $130,000.00 $10,500.00
002 Demolition and site clearing 02 $185,000.00 $185,000.00 $185,000.00 100.00% $0.00 $9,250.00
003 Concrete — foundations and slabs 03 $720,000.00 $720,000.00 $720,000.00 100.00% $0.00 $36,000.00
004 Masonry 04 $265,000.00 $265,000.00 $265,000.00 100.00% $0.00 $13,250.00
005 Structural steel 05 $890,000.00 $890,000.00 $890,000.00 100.00% $0.00 $44,500.00
006 Rough and finish carpentry 06 $210,000.00 $0.00 0.00% $210,000.00
007 Roofing and waterproofing 07 $305,000.00 $120,000.00 $185,000.00 $305,000.00 100.00% $0.00 $15,250.00
008 Glazing and curtain wall 08 $615,000.00 $245,000.00 $245,000.00 39.84% $370,000.00 $12,250.00
009 Interior finishes 09 $430,000.00 $0.00 0.00% $430,000.00
010 Plumbing 22 $275,000.00 $95,000.00 $95,000.00 34.55% $180,000.00 $4,750.00
011 HVAC 23 $395,000.00 $0.00 0.00% $395,000.00
012 Electrical 26 $220,000.00 $0.00 0.00% $220,000.00
013 Rooftop mechanical screen 05 $148,000.00 $0.00 0.00% $148,000.00
Totals $4,998,000.00 $2,348,000.00 $567,000.00 $0.00 $2,915,000.00 $2,083,000.00 $145,750.00

Reconciliation

Every figure on this application, checked against the contract, the schedule of values and the preceding period. This page travels with the document so nothing it reports can be discovered later.

1 warning(s).

RuleSeverityFinding ExpectedActualDifference Reference
COMPLIANCE-MISSING warning Form W-9: nothing on file. project compliance requirements
INFO-RETAINED info Retainage held to date: $145,750.00. $145,750.00
INFO-COMPLETE info Project is 58.32% complete by value. $58.32
INFO-MOVEMENT info Payment due moved -$610,750.00 against the previous application. -$610,750.00

Prepared with Massing Bill. Format follows the AIA G702/G703 line structure. Massing Bill is not affiliated with, endorsed by, or sponsored by The American Institute of Architects. AIA®, G702® and G703® are registered trademarks of the AIA.